GATE AG 2023 • Q7 MCQ • 2 Marks

Section 8: General Aptitude

Quantitative Aptitude

Subtopic: Ratios & Percentages

Question Statement:

To construct a wall, sand and cement are mixed in the ratio of 3:1. The cost of sand and that of cement are in the ratio of 1:2. If the total cost of sand and cement to construct the wall is 1000 rupees, then what is the cost (in rupees) of cement used?

Options:

  • (A) 400
  • (B) 600
  • (C) 800
  • (D) 200

Official Answer Key:

A

Step-by-Step Solution & Explanation

Let the quantity of sand = 3k, cement = k (mixing ratio 3:1). Let unit cost of sand = c, unit cost of cement = 2c (cost ratio 1:2). Cost of sand = 3k×c = 3kc; cost of cement = k×2c = 2kc. Total cost = 3kc+2kc = 5kc = 1000 ⇒ kc = 200. Cost of cement = 2kc = 400. Answer: (A) 400. *Distractor note:* (C) 800 results from mixing up which ratio (mixing vs cost) applies to which quantity.

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.

Launch CBT Mock Test