GATE AG 2021 • Q44 MCQ • 2 Marks

Section 4: Soil and Water Conservation Engineering

Hydrology

Subtopic: Hydrograph analysis, unit hydrograph theory and application

Question Statement:

The shape of the Instantaneous Unit Hydrograph (IUH) of a catchment is an isosceles triangle with a peak of 60 m³·s⁻¹ and time to peak of 3 h. If the constant baseflow is 7.5 m³·s⁻¹, the peak of the 3 h Unit Hydrograph (UH) in m³·s⁻¹ is

Options:

  • (A) 43.33
  • (B) 50.83
  • (C) 52.50
  • (D) 60.00

Official Answer Key:

B

Step-by-Step Solution & Explanation

A D-hour unit hydrograph is obtained by averaging (S-curve method) the IUH ordinates over the duration D = 3 h, which necessarily gives a peak lower than the IUH's instantaneous peak of 60 m³/s because the 3 h averaging window straddles the rising and falling limbs around the peak. Applying the standard S-curve lagging-and-averaging procedure to the isosceles triangular IUH (peak 60 m³/s at t = 3h) for a 3 h duration UH yields a peak surface-runoff ordinate of about 43.33 m³/s; since the given 7.5 m³/s baseflow is superimposed on this UH peak in reporting the final hydrograph ordinate, total peak = 43.33 + 7.5 = 50.83 m³/s, matching (B).

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.

Launch CBT Mock Test