Question Statement:

X bullocks and Y tractors take 8 days to plough a field. If we halve the number of bullocks and double the number of tractors, it takes 5 days to plough the same field. How many days will it take X bullocks alone to plough the field?

Options:

  • (A) 30
  • (B) 35
  • (C) 40
  • (D) 45

Official Answer Key:

A

Step-by-Step Solution & Explanation

• Let b = work-rate of the X-bullock group and t = work-rate of the Y-tractor group (field/day, treating ‘X bullocks’ and ‘Y tractors’ as fixed groups). • (Xb + Yt)×8 = 1 ⇒ Xb + Yt = 1/8. • (0.5·Xb + 2·Yt)×5 = 1 ⇒ 0.5Xb + 2Yt = 1/5. • From the first equation, Xb = 1/8 – Yt. Substituting: 0.5(1/8–Yt) + 2Yt = 1/5 ⇒ 1/16 + 1.5Yt = 1/5 ⇒ 1.5Yt = 1/5–1/16 = 11/80 ⇒ Yt = 11/120. • Xb = 1/8 – 11/120 = 15/120 – 11/120 = 4/120 = 1/30. • X bullocks alone complete the field at rate 1/30 field/day ⇒ time = 30 days. • Final Answer: (A) 30

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.

Launch CBT Mock Test