GATE AG 2010 • Q55 MCQ • 2 Marks

Section 4: Soil and Water Conservation Engineering

Hydrology

Subtopic: Hydrograph analysis, unit hydrograph theory and application

Question Statement:

[Linked 54–55] Assuming the above 1-h unit hydrograph to be triangular in shape with time to peak 1 hour, the peak of the 2-h unit hydrograph for the catchment in m³ s⁻¹ is

Options:

  • (A) 13.25
  • (B) 18.75
  • (C) 21.25
  • (D) 26.75

Official Answer Key:

B

Step-by-Step Solution & Explanation

The 2-h UH is obtained by lagging the 1-h UH by 1 hour and averaging the two ordinates (S-curve/superposition method). Taking a standard triangular shape with rise 0→1 h and recession 1→3 h (base = 3×time-to-peak), the ordinates of the original and the 1-h-lagged UH are summed and averaged; the resulting combined hydrograph peaks at t = 2 h, where U₁(2 h)=0 (already receded to zero... ) combined with the shifted curve's peak contribution gives a peak value of 18.75 m³/s, obtained directly from superposing the two 25 m³/s triangular ordinates offset by 1 hour and halving. Section 5 — Irrigation and Drainage Engineering

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.

Launch CBT Mock Test