GATE AG 2007 • Q48 MCQ • 1 Mark

Section 4: Soil and Water Conservation Engineering

Hydrology

Subtopic: Runoff estimation

Question Statement:

The maximum rainfall with a return period of 25 years is given below for a watershed having a time of concentration of 47.65 minutes: | Time (min) | 10 | 20 | 30 | 40 | 60 | |---|---|---|---|---|---| | Rainfall depth (mm) | 52.50 | 55.00 | 57.50 | 60.00 | 65.00 | In this watershed, 2.0 km² area has cultivated sandy soil ($C = 0.2$) and the remaining 3.0 km² has cultivated clay soil ($C = 0.7$). The peak rate of runoff from the watershed is:

Options:

  • (A) 4.29 m³ s⁻¹
  • (B) 5.41 m³ s⁻¹
  • (C) 42.99 m³ s⁻¹
  • (D) 54.13 m³ s⁻¹

Official Answer Key:

D

Step-by-Step Solution & Explanation

Rainfall depth at t=47.65 min (linear interpolation between 40 min:60.00 mm and 60 min:65.00 mm): d = 60.00 + (65.00−60.00)×(47.65−40)/(60−40) = 60.00+1.9125 = 61.91 mm. Intensity, i = d/(t_c in hours) = 61.91/(47.65/60) = 77.96 mm/h. Weighted runoff coefficient: C_w = (2.0×0.2+3.0×0.7)/(2.0+3.0) = 2.5/5.0 = 0.50. Rational formula (A in km², i in mm/h): Q = 0.278·C·i·A = 0.278×0.50×77.96×5.0 = ≈54.13 m³/s.

Practice This in Real CBT Exam Interface