GATE AG 2007 • Q44 MCQ • 1 Mark

Section 4: Soil and Water Conservation Engineering

Hydrology

Subtopic: Runoff estimation

Question Statement:

A recharge well of 300 mm diameter is constructed in a confined aquifer of 1000 m² d⁻¹ transmissibility. From the top of impermeable bed, the water level in the well is 50 m and the height of constant water level is 40 m. The constant water level occurs at a distance of 150 m from the center of the well. The possible maximum recharge rate is

Options:

  • (A) 3.16 m³ min⁻¹
  • (B) 6.32 m³ min⁻¹
  • (C) 9.48 m³ min⁻¹
  • (D) 12.64 m³ min⁻¹

Official Answer Key:

B

Step-by-Step Solution & Explanation

For a recharge (injection) well, the Thiem equation applies with the head reversed (buildup instead of drawdown): Q_r = 2πT(h_w − h₀)/ln(R/r_w), r_w = 0.15 m, R = 150 m, T = 1000 m²/d. Q_r = 2π(1000)(50−40)/ln(150/0.15) = 62,832/6.908 = 9095.8 m³/d = ≈6.32 m³/min.

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.